A German wholesaler, distributor or installer group can take Greek or Cypriot energy equipment only when the CE file, the energy label, the subsidy listing, the registers and the payment terms are settled. Subsidy, packaging and grid rules changed in 2026, so confirm each regulatory one with the authority before you ship.
- CE marking: the maker signs an EU declaration of conformity, affixes CE and keeps the technical file for 10 years. Low Voltage Directive Article 6 and EMC Directive Article 7 set this, and the first covers 50 to 1,000 V AC and 75 to 1,500 V DC. Pressure equipment above 0.5 bar, radio parts and machinery add their own acts (Machinery Regulation from 14 January 2027, radio cybersecurity from 1 August 2025).source
- Energy label: a supplier enters each new model in the EPREL database before sale (Regulation 2017/1369, Article 4). It keeps the data for 15 years after the last unit. Heaters, heat pumps and water heaters carry a printed label and fiche (Regulations 811/2013 and 812/2013), light sources a label on the pack (Regulation 2019/2015).source
- Solar thermal subsidy: the federal subsidy pays only for systems on BAFA's Solaranlagen list. Each needs Solar Keymark testing or certification by an ISO 17025 laboratory and, for liquid collectors, a yield of at least 525 kWh/m2 a year (Würzburg, 25 and 50 degrees C). Collectors with no front cover, such as pool absorbers, are excluded.source
- Heat pump subsidy: only models on BAFA's Wärmepumpen list qualify. They need an EN 14511 and EN 14825 test or a Keymark, EHPA, Eurovent, MCS or NF certificate, a seasonal efficiency of at least 181 percent for air units up to 12 kW, and a digital grid interface. Only natural refrigerants such as R290 qualify from 1 January 2028, and Union-origin pumps earn 15 extra points from the first quarter of 2027.source
- EU Battery Regulation: a storage system is an industrial battery, and its technical file must show tested safety (Article 12, from 18 August 2024). From 18 February 2027 a unit over 2 kWh needs a battery passport (Article 77) and every battery a QR code (Article 13). Supply chain due diligence now starts on 18 August 2027 (Regulation 2025/1561).source
- ElektroG: a maker with no branch in Germany cannot register with stiftung ear itself. It mandates one authorised representative in Germany, in writing and in German, for at least three months, and the representative files the registration once ear confirms the mandate. Batteries need their own registration by brand and category (stiftung ear battery guide).source
- Packaging: since 12 August 2026 the EU Packaging Regulation and the German VerpackDG replace the VerpackG. The producer is the first company in the German supply chain, so for a sale to a wholesaler it is the wholesaler. A maker shipping straight to an installer or consumer is the producer itself and names an authorised representative. Packaging with no system duty needs ZSVR approval from the end of 2027.source
- RoHS: electrical equipment, cables included, may not exceed the Annex II limits per homogeneous material (Directive 2011/65/EU, Article 4). They include 0.1 percent lead, mercury, hexavalent chromium, PBB and PBDE and 0.01 percent cadmium. Professionally installed solar panels are outside the scope, and REACH applies in parallel (Article 2).source
- F-gas: Annex IV to Regulation 2024/573 bars heat pumps charged with fluorinated gases in steps. From 1 January 2027 self-contained units up to 50 kW with a refrigerant of GWP 150 or more and split air-to-water units up to 12 kW are barred, unless site safety rules demand otherwise. Larger splits follow in 2029 and 2033, and any fluorinated charge in self-contained units to 12 kW ends in 2032.source
- Grid connection: VDE-AR-N 4105:2026-03, in force since 27 February 2026, is the national standard for low-voltage generating plants. It covers grid and plant protection and proof of electrical properties, each network operator builds it into its connection terms, and plants up to 800 VA of inverter power use a simplified form (F 1.2).source
- Trade defence: the EU repealed its anti-dumping and countervailing duties on Chinese solar glass in October 2026. The repeal is in Regulations 2026/2314 and 2026/2310, and duties paid since 22 July 2025 are refunded. The duties on Chinese modules and cells lapsed on 3 September 2018 (Commission reply to the Parliament). Confirm any other input with the authority.source
- Payment: a term over 60 days after delivery binds the supplier only if expressly agreed and not grossly unfair (section 271a BGB). For public buyers a term over 30 days needs an objective reason and over 60 days is void. Default starts 30 days after the due date and invoice (section 286), at 9 points above the base rate plus a 40 euro flat fee (section 288).source